NVIDIA DGX-Ready Data Center Program certified
Case Study
  • 7.1MW NVIDIA GB200 capacity delivered at CGK3A, Jakarta
  • 143 days from mobilization to Ready for Service (Phase 1 GB200 deployment)
  • 192kW per rack measured peak density at CGK3A
  • Up to 300kW per rack future design capability
  • Direct-to-chip liquid cooling supporting GB200-class and next-generation GPU architectures
  • Workloads live in the customer production environment